Notification of Hydrological Information on Lancang River (August 5, 2019)

The outflow of Jinghong Hydropower Station was recorded at 1100m3/s on 2nd August, 2019 and will remain so till 10th August.

The outflow will be decreased from 1100m3/s to 600m3/s-800m3/s from 11th to 15th, August, 2019 so as to conduct the maintenance for the transmission lines of the power grid and then will be gradually restored to normal operation status afterwards.  

Other related agencies and the riparian communities. In case of any other significant variation of the outflow, you will be informed in a timely manner.